The SaveOnEnergy Retrofit Program pays up to $1,000 per kW DC on behind-the-meter solar in Ontario. Stacked with the federal Clean Technology Investment Tax Credit and Accelerated CCA, the net first-year cost on a representative 50 kW install drops by roughly two-thirds. This is the playbook for Ontario installers running the Prescriptive Stream — eligibility, the application sequence, how the federal credits stack on top, and what the system has to do at commissioning to stay compliant for the next decade.
Executive summary
Three incentives apply to the same Ontario solar project, and they stack — provided the project is designed and sequenced for compliance:
- ▸SaveOnEnergy PV DER Incentive (Prescriptive Stream). Up to $1,000 per kW DC for microgeneration, $860 per kW AC for systems above 10 kW AC and up to 1 MW AC. Maximum 50% of eligible costs. Load displacement only — no net metering for the system's lifetime.
- ▸Clean Technology Investment Tax Credit (CT ITC). 20–30% refundable federal credit on capital invested in qualifying clean technology property. Applies through December 31, 2034. Provincial rebates reduce the cost base.
- ▸Accelerated Capital Cost Allowance (ACCA). First-year deduction at Class 43.1 (30%) or Class 43.2 (50%) rates under the Accelerated Investment Incentive. Phases out for property used after 2027.
The order matters. Each downstream credit is calculated against a base that has already been reduced by what came before it. Get the sequence wrong on the worksheet and the customer leaves dollars on the table — or worse, claims a credit they aren't entitled to and triggers a CRA recapture.
- ▸Apply before you start the project. Beginning work or signing a binding installation agreement before SaveOnEnergy pre-approval can reduce or void the incentive.
- ▸Design for load displacement only. Net metering is prohibited on the system for its operating lifetime. Plan the export control mechanism into the single-line diagram, not as an afterthought at commissioning.
- ▸Act as the Applicant Representative. Installers add real value by running the IESO portal workflow on the customer's behalf. The customer signs off and submits the invoice; everything in between is yours to drive.
- ▸Document for Red Seal labour. The 30% CT ITC tier requires at least 10% of project labour from Red Seal electrician apprentices. Without proof, the credit drops to 20%. Disclose which tier the customer is entitled to before the deal closes.
The SaveOnEnergy PV DER Incentive (Prescriptive Stream)
The Retrofit Program is delivered by the IESO and runs province-wide. The Solar PV DER Incentive sits inside the Prescriptive Stream and funds behind-the-meter solar that displaces onsite electrical load rather than exporting energy back to the grid.
2.1What the program pays
Incentive amounts are fixed per kW of installed capacity, with a hard cap on project size and a floor on minimum payout.
- ▸Microgeneration (≤10 kW DC): $1,000 per kW DC.
- ▸Small to medium (>10 kW AC and ≤1 MW AC): $860 per kW AC.
- ▸Larger projects (>1 MW AC): eligible, but the incentive is capped at 1 MW AC.
- ▸Funding floor and ceiling: minimum $500 incentive value; maximum 50% of eligible project costs.
2.2What qualifies (and what doesn't)
- ▸Eligible installations: rooftops, parking canopies, and wall-mounted systems.
- ▸Not eligible: ground-mounted PV and Building-Integrated Photovoltaics (BIPVs).
- ▸Operating model: load displacement only. Net metering and other export-compensation arrangements are prohibited for the system's lifetime once approved.
2.3Deadlines and pre-project commitments
Pre-approval timing drives the entire workflow. The IESO requires an application before the project begins; any binding work signed before pre-approval risks the incentive.
- ▸Projects pre-approved before January 1, 2025 must be completed by December 31, 2025.
- ▸Projects pre-approved on or after January 1, 2025 must be completed and invoiced for payment within two years of pre-approval.
- ▸Starting work before pre-approval may result in reduced or denied incentives.
The application workflow for installers
The installer is best positioned to act as the customer's Applicant Representative — registering in the IESO Retrofit Portal, assembling documentation, and managing the application from quote through invoice. The customer signs the Participant Agreement and submits the invoice; everything else is the installer's scope.
- 01Introduce the program. Position the Retrofit Program as a payback accelerator. The conversation lands harder when the SaveOnEnergy line is paired with the federal ITC and ACCA stack from the start.
- 02Confirm the right incentive. Check that the project meets the $500 minimum incentive floor and matches the Prescriptive Stream criteria.
- 03Complete the Solar PV DER worksheet. Select the closest applicable location, orientation, and tilt angle. The worksheet outputs two values — Energy Factor and Peak Demand Factor — that go directly into the Retrofit Portal.
- 04Assemble the pre-project package. Quotes and cost estimates, completed worksheet, written confirmation of load-displacement-only operation, rooftop/canopy/wall mounting, LDC and code compliance, permits in motion, manufacturer spec sheets, photos of the install area, and any eligible engineering or design costs.
- 05Register in the Retrofit Portal. Both the installer (Applicant Representative) and the customer (Applicant) need accounts. Sign up, confirm by email, set MFA, select the appropriate account type.
- 06Enter project and measure details. Project information, facility details, prescriptive measures, the Energy Factor and Peak Demand Factor from the worksheet, the estimated project cost. Upload quotes and spec sheets.
- 07Review the estimated calculations. Walk the customer through the portal's estimated savings and incentive value before forwarding for sign-off.
- 08Customer sign-off. Forward the application via the portal. The Applicant reviews, accepts the Retrofit Program Participant Agreement, and submits to IESO.
- 09Pre-approval. IESO typically returns a decision in three to four weeks. Edits may be requested. A confirmation email lands when pre-approval is granted.
- 10Build the project. Work may proceed after submission, but the safer path is to wait for pre-approval before signing binding agreements or breaking ground.
- 11Post-project submission. Customer invoice, disposal documents, energy savings calculations, as-built single-line diagram, commissioning checklist from the DER authority, Connection Impact Assessment, and written confirmation that the system is not net-metering. Forward to the customer for review and final submission.
- 12Invoice and follow-up. IESO requests the invoice once the project is approved. Only the customer can submit it through the portal. Payment lands in 1–3 weeks by e-transfer or 8–12 weeks by cheque. Follow up afterwards on performance — and on the next project.
- Phone: 1-844-303-5542 (Mon–Fri, 8:30 am – 5:00 pm ET)
- Email: retrofit@ieso.ca
- Portal: retrofitportal.ca
Stacking with federal tax credits
The SaveOnEnergy incentive is treated as government assistance under federal tax law, which means it reduces the capital cost base used to calculate both the Clean Technology Investment Tax Credit and the Accelerated Capital Cost Allowance. The credits then stack in sequence — each one applied against the cost base remaining after the previous step.
4.1Clean Technology Investment Tax Credit (CT ITC)
A refundable federal tax credit on capital invested in new clean technology property in Canada. Applies to property acquired between March 28, 2023 and December 31, 2034. Solar PV qualifies under Class 43.1, subparagraph (d)(vi), when sited and used exclusively in Canada.
- ▸Credit rate: 20% base; 30% with Red Seal apprenticeship labour compliance (minimum 10% of project labour hours from Red Seal electrician apprentices).
- ▸Claimed by: the customer, on the T2 Corporate Income Tax Return.
- ▸Installer documentation: building permits, interconnect agreements, Red Seal apprenticeship timesheets, commissioning documents, invoices, and proof of payment.
- ▸Base for calculation: capital cost minus the SaveOnEnergy rebate.
- ▸Refundability: fully refundable — paid out even if the customer has no tax owing.
4.2Accelerated Capital Cost Allowance (ACCA)
Also called the Accelerated Investment Incentive (AII). Allows a higher first-year depreciation deduction on qualifying property. Administered by CRA at tax time — the installer's involvement ends at handing over the documentation pack.
- ▸Class 43.1: 30% rate.
- ▸Class 43.2: 50% rate (property acquired before 2025).
- ▸Accelerated Investment Incentive Property (AIIP): new property acquired after November 20, 2018 and available for use before 2028.
- ▸Phase-out: enhanced CCA tapers from 2024; no longer available for property used after 2027.
- ▸Base for calculation: capital cost minus the SaveOnEnergy rebate minus the CT ITC claimed.
- ▸Recapture risk: deductions exceeding the adjusted capital cost can trigger recapture. The customer's accountant should size the Year-1 deduction to avoid it.
4.3Worked example: a 50 kW commercial rooftop
The table below tracks a representative $100,000 commercial rooftop project through the stack — provincial rebate first, federal credit second, accelerated depreciation third. The Year-1 figures shown are illustrative; project-specific numbers should be sized against the customer's actual tax position by their accountant.
The net Year-1 outcome is a project that has effectively repaid roughly two-thirds of its capital cost before the first kilowatt-hour of displaced load is counted. Subsequent CCA deductions continue against the diminishing balance; the energy bill displacement runs in parallel for the system's operating life. On most commercial sites in Ontario, this puts payback in the four-to-six-year range before any battery economics are layered on top.
Where batteries fit — and where Sponge fits
The SaveOnEnergy PV DER incentive does not cover batteries. The Clean Tech ITC and ACCA do. That is the design space.
Adding a battery to a load-displacement solar project loosens the constraint that has historically bounded system size: the daytime load. A site with 60 kW of daytime demand and a 250 kW roof can take the full 250 kW of solar — provided the battery and the controller absorb the surplus and the export stays at zero. The battery then earns its own payback through peak shaving and energy arbitrage against the host's rate environment.
Two Sponge capabilities map directly to the SaveOnEnergy compliance envelope:
- ▸Zero-Export Control. A one-time commissioning service that activates export control on the Sponge EMC. The controller reads power at the point of interconnection through a revenue-grade meter and modulates inverter output to follow facility load in real time. Backfeed never reaches the meter. This is what makes a 250 kW system on a 60 kW load legal under the program's load-displacement-only requirement.
- ▸Optimization Subscription. Where a battery is added, the Sponge optimization layer dispatches it against demand charges and time-of-use arbitrage on a continuous, forecast-driven basis. The EMC's control loop runs the same edge-local autonomy used on BC Hydro ESI deployments — meaning the controller continues to manage exposure even when the cloud connection is interrupted.
Zero-Export Control and the Optimization Subscription are mutually exclusive: a site runs one or the other, not both. Pure load-displacement solar uses Zero-Export. Sites adding batteries to extend the project beyond daytime load use the Optimization Subscription, which includes export control as a baseline capability.
The SaveOnEnergy PV DER Incentive rewards solar installers who design for compliance from day one and run the application sequence on the customer's behalf. Stacked with the Clean Tech ITC and ACCA, the project economics close fast — provided the load-displacement obligation is engineered into the system, not bolted on at commissioning. That is the part Sponge handles.
Next Step
Book a 30-minute design review
Walk through your next Ontario load-displacement project with our team. We'll cover the SaveOnEnergy worksheet, the federal stack, and the Sponge EMC commissioning scope end to end.
Book a review call →